Construction & CDM
What Is a Construction Phase Plan and When Do You Need One?
Guidance dated 11 September 2026
A construction phase plan sets out how health and safety will be managed during construction work. Under CDM 2015 in Great Britain, it is required for every construction project and must be in place before the construction phase begins. Small projects are not exempt simply because they are short or do not need notification to HSE. [32]
The plan should be proportionate. A straightforward repair may need a concise document. A complex project with several contractors needs more detailed coordination and control.
What work counts
Construction work is wider than new buildings. It can include refurbishment, alteration, repair, maintenance and installation work falling within the CDM definition. Do not assume that calling a job facilities maintenance removes it from the regulations. [33]
Consider the scope early enough to plan the work properly. If there is uncertainty about whether an activity is construction, resolve it before appointing the team and setting the start date.
Northern Ireland uses the Construction (Design and Management) Regulations (Northern Ireland) 2016. Projects there should be planned under that framework. [35]
Who prepares the plan
For a project involving only one contractor, that contractor prepares the plan. Where more than one contractor is involved, the principal contractor prepares it. The client must ensure an appropriate plan is prepared before the construction phase starts. [33]
A consultant can help develop the document, but the responsible contractor needs to own the arrangements. A plan written without input from the people organising the work may miss how the site will actually run.
Agree who updates it and how changes are communicated. There should be a current version that site management can access throughout the work.
What the plan should contain
The plan must describe the health and safety arrangements, site rules and relevant measures for particular risks listed in CDM. [33]
Useful content normally explains the project, responsibilities, coordination, access, welfare, emergency arrangements and how significant risks will be managed. It should show how contractors exchange information and how the work is monitored.
For an occupied premises, explain how construction is separated from normal operations. Consider deliveries, temporary routes, fire precautions, services and handovers. A statement that the site will be secure is insufficient if nobody has agreed the boundary or access arrangements.
Keep supporting documents connected. Detailed RAMS can explain particular tasks, while the construction phase plan explains how the project is organised. Avoid copying large quantities of task information into the plan if that makes the overall arrangements harder to find.
How it differs from other project information
Pre-construction information is provided to help designers and contractors understand the project and relevant existing risks. The construction phase plan explains the arrangements for managing the construction phase. [33]
A health and safety file, where required, supports future work on the structure. It is a different document with a different purpose. None of these is automatically replaced by a contractor’s general company policy.
Establish which documents are needed and who is preparing each one. Similar names often create gaps because people assume another document already covers the requirement.
Is the plan needed only for notifiable projects
No. Notification and the construction phase plan are separate requirements. A project is notifiable where the construction work is scheduled to last longer than 30 working days and involve more than 20 workers at any one time, or exceed 500 person-days. [34]
A short project below those thresholds still needs suitable planning. The notification thresholds should not be used as a boundary between work that needs managing and work that does not.
Keep the plan useful as the work develops
Review the plan as the programme, contractors, methods or site conditions change. Check that the arrangements described are available in practice before the relevant phase starts.
For example, if refurbishment work moves into a new occupied area, confirm the revised boundary, escape arrangements and communication with the occupier. Do not assume the original setup remains suitable simply because the overall project title is unchanged.
FAQs
Do I need a plan for a one-day job
Yes, if it is a construction project within CDM. The plan can be proportionate to the work; duration alone does not create an exemption.
Can RAMS replace the construction phase plan
Not automatically. RAMS explain task risks and methods. The construction phase plan must address the required project-level management arrangements.
Can SSS write the plan for the contractor
We can support preparation, but the contractor or principal contractor must provide the operational information, agree the arrangements and fulfil its duties.
How Secure Safety Solutions can help
We help with construction phase plans, RAMS, pre-construction information and site health and safety support. Tell us what is being built or changed, who is involved and how the premises will be used during the work.
Discuss your construction phase plan
Sources and further reading
- [32] HSE: Construction phase plans CIS80
- [33] HSE: Planning for construction work
- [34] HSE: Commercial clients and notification thresholds
- [35] HSENI: CDM Northern Ireland Regulations 2016
General guidance. The arrangements you need depend on your activities, premises and location.