Construction & CDM
CDM 2015: What Clients Need to Know
Guidance dated 11 September 2026
If your organisation commissions construction work as part of its business, it is normally a commercial client under CDM 2015. You have duties that begin during planning and continue through the project. Appointing a building contractor does not remove them. [34]
You do not need to become a construction specialist to be a good client. You do need suitable arrangements, competent appointments, enough time and resources, and a way to check the project is being managed properly.
Recognise when your business becomes the client
CDM can apply to refurbishment, repairs and other construction activities as well as new buildings. A retailer altering a unit, a school commissioning building work and an engineering business extending a workshop can all be commercial clients.
The duties apply to projects of all sizes. Notification thresholds determine whether HSE must be notified, not whether CDM applies.
This guide covers Great Britain. Northern Ireland has its own CDM 2016 regulations. Domestic clients also have different arrangements, with duties normally passing to other dutyholders; do not apply those domestic provisions to ordinary business projects. [35,36]
Make appointments early enough to matter
Where a project involves, or is reasonably foreseeable to involve, more than one contractor, the commercial client must appoint a principal designer and principal contractor in writing. The appointments must be made as soon as practicable and before the construction phase begins. [37]
More than one contractor does not mean they must all be on site at the same time. Think about the whole project, including separate trades and subcontractors.
Check relevant skills, knowledge, experience and organisational capability. Ask how the proposed team will manage the project’s actual risks, rather than relying only on a logo, membership or previous relationship.
Provide useful pre-construction information
The team needs relevant information about the site and the work. This can include existing plans, known services, asbestos information, structural matters, access restrictions and arrangements for ongoing occupation.
Identify gaps early. If intrusive work is planned but existing information does not address the area to be disturbed, arrange appropriate investigation before the work depends on it. Forwarding a folder of unrelated records does not resolve missing information.
Make the information available in time to influence design, pricing and methods. A risk disclosed on the first morning may leave the contractor without the time or resources to address it safely.
Set realistic project arrangements
Allow sufficient time and resources. Ensure suitable welfare facilities will be available and that the construction phase plan is prepared before construction begins. Maintain and review the management arrangements during the project. [34]
Your oversight should match the project. Agree who reports progress, what decisions need client input and how concerns will be escalated. For an occupied building, make sure the project team coordinates with the people running the business.
A programme that assumes all work can take place alongside normal operations needs testing. Noise, dust, service shutdowns, access and emergency routes may require different phases or temporary relocation.
Understand the different principal roles
The CDM principal designer manages and coordinates health and safety during the pre-construction phase. The principal contractor manages and coordinates the construction phase. [36]
In England, building regulations also create separate dutyholder roles, including roles with similar titles. Do not assume that a CDM appointment automatically fulfils a separate building regulations appointment. Confirm the required scope and competence for each role. [63]
Likewise, employing a health and safety adviser does not automatically appoint that adviser as principal designer or principal contractor. Make the agreed support and legal appointments explicit.
Plan the handover as well as the start
Where a health and safety file is required for a project involving more than one contractor, ensure it is prepared and handed over appropriately. Keep it available to those who need it for future work. [37]
Check that unresolved safety matters, relevant records and ongoing restrictions are addressed before the project team leaves. A tidy site and a completed invoice are not the whole handover.
Agree early what information will be needed. Recovering it after designers and subcontractors have moved on can be much harder.
FAQs
Does CDM apply if the project is not notifiable
Yes. Commercial client duties apply regardless of whether the project crosses the HSE notification thresholds.
Can the main contractor take all our client duties
Appointing a contractor does not remove commercial client duties. The contractor has its own responsibilities and the client must fulfil its role.
Do we need a principal designer for a single contractor project
CDM requires a principal designer appointment where more than one contractor is involved or reasonably foreseeable. Other client and designer duties still apply to single contractor projects.
How Secure Safety Solutions can help
Secure Safety Solutions supports clients and project teams with pre-construction information, construction phase plans, RAMS and site inspections. We can help identify the health and safety arrangements needed and work alongside your appointed dutyholders.
Talk to us about construction support
Sources and further reading
- [34] HSE: Commercial clients and notification thresholds
- [35] HSENI: CDM Northern Ireland Regulations 2016
- [36] HSE: Managing health and safety in construction L153
- [37] CDM Regulations 2015: Regulations 4 5 and 12
- [63] GOV.UK: Building regulations dutyholders and competence
General guidance. The arrangements you need depend on your activities, premises and location.